A contractor employed 60 men to do a certain job in 15 days. How many men working at the same rate would he need to complete the work in 4 days?
A
240
B
225
C
60
D
16
E
12
Answer:B
Practice more with TestDriller

To see detailed solution to this question and thousands of other questions offline, download TestDriller Common Entrance. Practice rigorously for the National Common Entrance Examination for admission into Junior Secondary School, enjoy educational games, dictionary, compete with your peers, win prizes and more.